Corridor at a glance
The TransAndes Corridor in numbers
Base-case figures from the current feasibility model: what the corridor costs, what it carries and when it runs. Hover over any chart for detail.
~4,870 kmnetwork, all sections
~US$37.8 bntotal investment, base case
5countries, one company per country
~46 Mtbulk cargo a year at full operation
~410,000containers (TEU) a year, both ways
2034first trains, base case
By country
Investment, US$ billion
What the trains carry
Bulk cargo at full operation, million tonnes a year
Ramp-up to full volume
Share of full-volume bulk cargo carried in each operating year
Timeline
Base case
Now – 2027PreparationGovernment partners per section, engineering, permits and financing.
2028 – 2033ConstructionAbout 6 years. Supplier plants for cement, sleepers and precast are built first, along the line.
2034First trainsOperations start when the main line is complete; shippers switch routes as contracts allow.
Operating year 10Full volumeAbout 46 Mt of bulk cargo and 410,000 containers a year, in both directions.
Built for low cost per tonne
Design parameters that keep operating cost low for the life of the line
1.2 %maximum grade
Standard gauge1,435 mm, heavy-haul
Electrifiedelectric traction
Double trackon mountain grades and major crossings
Container-readytunnels sized for double-stack
Figures: TransAndes Corridor feasibility model, base case, November 2026. Investment covers infrastructure (track, tunnels, viaducts, power and signalling). Ballpark values for planning, to be validated by an independent feasibility review; not an offer or a financial projection. The route shown elsewhere on this site is schematic; the final alignment is subject to studies and government agreements.
The TransAndes Corridor is developed by Transandes Development Corporation (TADC), a brand of Transandes Ventures LLC (Delaware, USA). Nothing on this site is an offer, solicitation or invitation to invest.